Skip to main content

Annual Plan Events

Annual Plan Calendar - Event Updates

  • Two Steps in Using Annual Plan Calendar:
    • Create/Maintain a Calendar
    • Apply the Calendar to frequency
  • A/O/B/N is not configurable
  • Offsets use workdays

Calendar Events

  • Dates can be added or removed from a Calendar through Events
$CALENDAR:ADD,Company Holiday Calendar,05/25/2025; 05/25/2026; 05/25/2027; 05/25/2028; 05/25/2029,ocadm,opconxps
$CALENDAR:DEL,Company Holiday Calendar,05/25/2025; 05/25/2026; 05/25/2027; 05/25/2028; 05/25/2029,ocadm,opconxps
  • Scenarios:
    • A Job needs to run 10 working days after the 15th of month
    • A Null Job scheduled to run on the 15th could submit:
$CALENDAR:ADD,Company Holiday Calendar,[[$SCHEDULE DATE(+10wd)]],ocadm,opconxps
  • A Job needs to run the working day before a different Job scheduled for the 15th-B
    • Date calculation tool – Chronoman

Calendar Add Event Definition

Enterprise Manager

Details

Annual Plan Frequency

Forecast Annual Plan

Calendar Add Event Definition